PNRR C9 implementation deadlines in 2026: what can still be saved

For PNRR C9 beneficiaries, 2026 comes down to two dates: the end of implementation (30 June or 31 July) and the payment cut-off, 30 October.

Northdan Soft is a software supplier, not a funding consultancy, and is not affiliated with any managing authority or development agency. Programme information is indicative — always check the conditions in the programme's official applicant guide.

Two normative acts define the 2026 calendar for beneficiaries of PNRR C9 digitalization grants — PNRR being Romania's National Recovery and Resilience Plan. Ordinul 607/2026 (a MIPE ministerial order) fixed the completion of implementation at 30 June 2026, and 31 July 2026 applies exclusively to projects that filed an extension request in time. Ordinul 963/2026 established that payments are made no later than 30 October 2026. Verified on 30 July 2026: both implementation dates have passed, and the stakes have shifted to closing projects impeccably: signed acceptances, working software, a complete disbursement file. This is where a disciplined vendor counts. Our on-time implementation package exists for exactly these situations: we take over the development or completion of the software solution and hand over the acceptance protocols, reports and proof-of-operation evidence the authority requests at reimbursement. We are not funding consultants and we make no promise about the outcome of your claim; we are the technical supplier, and we say at the outset what the time left actually allows.

Let’s talk about your project

Message us on WhatsApp or send an email — you talk directly to a developer.

office@northdan.com · +40 752 070 247

How we help

Scope fixed before the clock runs out

When the cut-off is close, the first working session settles what is realistically deliverable by that date, and we build to that perimeter instead of to the full wish list.

Acceptances and proof of operation

We hand over the software together with acceptance protocols, manuals and functionality screenshots — precisely the material the payment file demands.

Communication aligned with your consultant

We keep your funding consultant informed of delivery status, so the reimbursement claim is filed without coordination hiccups.

The two orders dictating your calendar

Ordinul 607/2026 settled the extension debate: implementation of PNRR C9 projects ended on 30 June 2026, with 31 July 2026 reserved for projects that had filed an extension request in time. There is no third date, and activities unfinished by then fall out of the disbursement.

Ordinul 963/2026 completes the picture on the financial side: payments to beneficiaries are made by 30 October 2026. The August–October interval is therefore the administrative window in which reimbursement files must be flawless.

What “implementation completed” means in practice

Software paid for but not working is not a completed implementation. The authority looks at actual delivery: the application installed and usable, acceptance signed, staff trained where the project requires it, invoices matched to the approved budget.

The most frequent problems we see: features promised in the application but never delivered by late vendors, vague acceptance documents, and mismatches between invoice wording and budget lines. All three can be corrected if you act in time.

If your project is running late

The first step is a candid diagnosis: what has been delivered, what is missing, what can still be completed before financial closure. We also take over projects begun by other vendors, provided a quick technical audit runs at the start.

What cannot be rescued is worth saying plainly: a cost absent from the approved budget does not become eligible because it was delivered quickly, and after the payment window closes there is no procedure for recovering an otherwise correct expense.

Frequently asked questions

What is the final implementation deadline for PNRR C9 digitalization projects?

Under Ordinul 607/2026, implementation completed on 30 June 2026, with 31 July 2026 applying only to projects that filed an extension request in time. Check your financing contract and your correspondence with the authority to see which of the two dates applied to you.

Until when are payments made on the PNRR C9 grants?

Ordinul 963/2026 sets 30 October 2026 as the cut-off for making payments. That is why autumn 2026 belongs to verifying reimbursement files, not to developing new features.

Can Northdan take over a project abandoned by another software vendor?

Yes, after a preliminary technical audit: we evaluate the existing code and deliverables, state transparently what can be finished in the time left and contract only what we can guarantee. We would rather give an honest “no” than a promise that compromises your disbursement.