PNRR for companies in 2026: nothing left to apply for, two deadlines left to meet
None of the PNRR lines aimed at companies still accepts applications. What remains are signed contracts, two calendars that must not be confused, and one figure that circulates wrongly.
As of 30 July 2026, no line of Romania's National Recovery and Resilience Plan aimed at companies still accepts applications; what is running are contracts signed in earlier rounds. For a beneficiary in that position the year turns on two separate dates that must never be mixed up: the implementation deadline, by which the software has to be delivered and formally accepted, and the payment deadline, by which the reimbursement file is filed. On the Component 9 SME digitalization line, implementation is governed by Ordinul MIPE nr. 607/2026 — 30 June 2026 as the general term and 31 July 2026 for projects granted an extension — while payment runs to 30 October 2026 under Ordinul MIPE nr. 963/2026. For a company without a PNRR contract this page carries a single useful message: do not wait for a reopening that no authority has announced; look instead at the calls receiving applications right now. They are listed below with their deadlines, together with the explanation for the EUR 20,000–100,000 figure you will meet presented as current on many pages.
Let’s talk about your project
Message us on WhatsApp or send an email — you talk directly to a developer.
office@northdan.com · +40 752 070 247
How we help
Two calendars, kept apart
We separate what must be accepted by the implementation deadline from what may wait until the payment deadline — confusing the two is what forfeits funding.
Every status tied to the act that sets it
Each deadline on this page is linked to the MIPE order that governs it, so you can verify it yourself rather than take our word for it.
We take over the remaining development
If the software part of an active contract is stuck, we restructure delivery into short iterations and hand over the technical documents the reimbursement file needs.
We also say no
When the time left no longer allows delivery, we put that in writing before signing. An optimistic estimate now becomes an ineligible cost three months later.
What is closed, what is receiving applications now, and until when
Closed for applications and now in implementation or reimbursement: the Component 9 SME digitalization line, with the deadlines above; the advanced digital technologies line of the same component, covering projects between EUR 500,000 and EUR 3,000,000; and the call dedicated to non-governmental organisations, whose implementation is governed by Ordinul MIPE nr. 609/2026. Each has its own page here, with its own dates.
Investment 19 of Component 7 works differently and is the most frequently misdescribed. It is not a grant: it is de minimis aid of at most EUR 17,000 per undertaking, granted exclusively as employee training programmes across nine technology domains, run by the Romanian Digitalization Authority (ADR). The company receives no money in its account and cannot redirect the amount to licences, equipment or software development. The official project page states that the submission period for support requests has ended and that SMEs can no longer file requests through the dedicated portal, and the implementation period declared there is December 2022 – December 2025.
Receiving applications right now, outside PNRR, are two lines relevant to a company that wanted digitalization. POCIDIF Action 2.1 is open from 30 June 2026, 15:00, to 30 September 2026, 17:00, under the guide approved by Ordinul MIPE nr. 965/23.06.2026, with a minimum non-repayable value of EUR 200,000 and a ceiling of EUR 1,500,000 for projects whose result is an innovative software solution; it addresses firms holding ICT CAEN codes, not any company. SME Eco-Tech accepts applications until 24 September 2026, 20:00, with a grant of at most 40% capped at CHF 50,000, that is RON 267,240.
The EUR 20,000–100,000 figure: what it is and what it is not
That band still appears on pages presented as current, sometimes split by company size. What we can state as verified is what it is not: it describes no call receiving applications at this moment. On the call open now for software developers, POCIDIF Action 2.1, there is no tier below EUR 200,000, and the ceiling for a software result is EUR 1,500,000.
The band belongs to the PNRR C9 I3.1 call for digitalizing SMEs outside the IT sector: applications were received between 15 February and 30 June 2023 and the call has been closed ever since, with its own page here. Two further closed documents circulate around it, disambiguated on our POC 2014-2020 archive page. The practical conclusion is unchanged: a plan sized at EUR 100,000 on the assumption of an open call rests on a figure with no call behind it.
The same caution applies to the EUR 3,000,000 figure, which appears on two different programmes at once. On the PNRR advanced-technologies line it belongs to a closed call; on POCIDIF Action 2.1 it is granted only to projects whose result is an innovative hardware product manufactured by the beneficiary, and the portion above EUR 1,500,000 must be justified by financing the production line. A software company budgeting on EUR 3,000,000 is reading somebody else's ceiling.
The order of operations in a contract's final months
Delivery and acceptance first, reimbursement second. The software must be put into production and formally accepted by the implementation deadline applicable to your contract; only then is the payment claim file assembled, against its own later deadline. Reversing that order is the most common mistake we see: beneficiaries preparing reimbursement documents for features not yet delivered.
What we do at this stage as a vendor: we re-plan deliveries into short iterations with written acceptance criteria, sign acceptance protocols as features reach production, and hand over the technical documentation, invoices and reports in the form the file requires. The deadlines that actually apply remain those in your financing contract and in the MIPE orders, not those on a marketing page.
One limit stated upfront: we do not sign acceptance protocols, conformity declarations or test reports for software delivered by another supplier. We can take over the remaining development under our own contract and audit what we find, but our signature covers only our own work. A beneficiary who needs the opposite has a contract problem, not a supplier problem.
What to prepare now if you have no contract and are waiting for a new call
A new wave of digitalization funding becomes real only when an official guide is published; until then, any circulating calendar is an estimate. What depends on no guide and never expires: an inventory of the processes to digitalize, ranked by the workload they consume today, a technical specification of the solution, and a budget by cost category built on real offers.
Funding guides require at least two dated offers or market analyses to justify prices; a company that already holds the written specification collects those offers in days rather than weeks. The rest of the dossier — the application, the business plan, the filing — remains yours and your consultant's, not ours.
Frequently asked questions
Is any PNRR call still open to companies in 2026?
No. Every PNRR line relevant to companies is closed for applications, and contracted projects are in implementation or reimbursement. The calls receiving applications at this moment belong to other programmes: POCIDIF Action 2.1 until 30 September 2026 for firms with ICT CAEN codes, and SME Eco-Tech until 24 September 2026. The full calendar for the year sits on our funding calendar page.
What separates the two C9 lines for companies?
Scale and audience. The SME digitalization line targeted technology adoption in firms outside the IT sector, with small and numerous projects; the advanced digital technologies line funded projects between EUR 500,000 and EUR 3,000,000, where the stake is development rather than purchase. Both are closed for applications, and their separate pages carry the deadlines specific to each.
What does Investment 19 actually provide, and why can it not buy software?
Because the official wording leaves no opening: the de minimis aid of at most EUR 17,000 per undertaking is granted exclusively as training programmes in the nine technology domains listed by ADR. The company reimburses no invoices and receives no sum in its account; it receives the value of the courses its employees attend, counted against its de minimis ceiling. A supplier tying a software offer to this investment is selling outside the scheme.
Our PNRR project is behind schedule. What is realistic?
Start from a status check by feature rather than by percentage: what is in production, what is written but untested, and what does not exist at all. From that list you decide what can still be delivered and accepted before your contractual deadline, in the order that secures the most eligible cost. We take over the remaining development under our own contract, deliver in short iterations, and put in writing what no longer fits.
Where do I find the MIPE orders that set my project's deadlines?
They are issued by the Ministry of Investments and European Projects and published on the programme's pages; for the SME digitalization line the relevant ones are nr. 607/2026 for implementation and nr. 963/2026 for payment, and for the NGO call, nr. 609/2026. The practical advice stays the same: read them together with your own financing contract, because addenda can change what applies to your project.
Packages for this programme
Services for the software component
Similar pages
Related resources
Let’s talk about your project
Message us on WhatsApp or send an email — you talk directly to a developer.
office@northdan.com · +40 752 070 247